Study Timetable
Comprehensive flood studies take some time to complete, incorporating detailed technical analysis, community consultation activities, study documentation and review process.
Set out below is an indicative timetable which the project will follow, with key project stages and their proposed completion dates.
STAGE 1:Data Collection and Assessment and Community Consultation
Completion by April 2014 - COMPLETED
STAGE 2:Hydrological Modelling
Completion by July 2014 - COMPLETED
STAGE 3:Hydraulic Modelling
Completion by September 2014
STAGE 4:Climate Change Analysis
Completion by October 2014
STAGE 5:Draft Flood Study Report
Completion by End 2014
STAGE 6:Public Exhibition - Workshops - Presentation on Draft Report
2014
The completion of the study will see the Final Report to be presented to Council for adoption.