Study Timetable

Comprehensive flood studies take some time to complete, incorporating detailed technical analysis, community consultation activities, study documentation and review process.

Set out below is an indicative timetable which the project will follow, with key project stages and their proposed completion dates.

STAGE 1:Data Compilation

Completion by September 2016

STAGE 2:Hydrological Modelling

Completion by January 2017

STAGE 3:Hydraulic Modelling

Completion by July 2017

STAGE 4:Climate Change Analysis

Completion by August 2017

STAGE 5:Properties at Risk Analysis and Cumulative Development Analysis

Completion by September 2017

STAGE 6:Draft Flood Study Report

Completion by October 2017

STAGE 7:Public Exhibition � Workshops � Presentation on Draft Report

Completion by December 2017

The completion of the study will see the Final Report to be presented to Council for adoption.